Offshore wind farm firm asks for five-year extension to work

Seagreen plans to bring energy from offshore turbines ashore at Cockenzie <i>(Image: SSE)</i>
Seagreen plans to bring energy from offshore turbines ashore at Cockenzie (Image: SSE)
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.
Close Icon

Find, save and share Public Notices that affect you in the area.

Search the Public Notice Portal What is the Public Notice Portal?

What is the Public Notice Portal?

The Public Notice Portal carries statutory public notices published in local newspapers and is the fastest and most effective way of finding out what is happening in YOUR neighbourhood.

Search the Public Notice Portal

OFFSHORE windfarm operators have asked for a five-year extension to start work on their East Lothian site due to "industry uncertainty" – a month before permission runs out.

Seagreen Wind Energy Limited (SWEL) was given the go-ahead to bring power from 36 planned wind turbines onto shore at the former Cockenzie Power Station site as part of its Seagreen 1A project in 2020.

At the time, part of the conditions required work to begin within five years of permission being granted.

But with delays to creating the final wind turbines, the firm is now asking for a new start date estimated between 2029 and 2032.

In a report provided to East Lothian Council, SWEL said that consents granted to the project phase needed to change because of delays.

It said: “Due to uncertainties in the offshore wind farm (OWF) industry and challenges specifically facing the development of the final 36 turbines and associated infrastructure consented as part of Seagreen Alpha and Bravo, but not yet constructed, SWEL are proposing an extension of the
construction window for Seagreen 1A.”

Seagreen Wind Energy Ltd is a joint venture between SSE Renewables and Total Energies which was awarded exclusive development rights in the Firth of Forth by the Crown Estate in 2010.

It is one of a number of offshore projects which have been granted permission to build substations at the former power station site, which was bought by East Lothian Council as a major economic development site seven years ago.

Reports submitted to the council say that large parts of the £3 billion offshore wind farm project, which will bring energy onshore in Fife as well as Cockenzie, have been completed.

However, it said that delays meant it now needed to extend the start date for the East Lothian-linked work to allow it to carry on.

The application, to change part of its consent conditions to delay the need to start construction for another five years, has been lodged with council planners for approval.